GE Housatonic Restoration-For information regarding the three accepted grant proposals submitted by New Milford. Find the proposals under Project Proposals and ideas on the left side of the web page. The three proposals are: P-28 Pickett District Park Pedestrian Link, P-30 Young's Field Park Riverwalk and Greenway and P-31 Sega Meadows Park River Enhancement.
Church Street - Streetscape/Pedestrian Safety Imporvements. Value $276,025 OPM-STEAP Grant monies.
Whittlesey Avenue - Streetscape/Pedestrian Safety Imporvements. Value $500,000 DECD-Small Cities monies.
Housatonic Avenue Infrastructure Improvements - Design and construction of Water/Sewer extensions, sanitary sewer pump station and roadway improvements. Value $2,200,000 Grants DECD Urban Action. Total Project value $4,400,000.
Aspetuck Ridge Road Bridge [southern end] - Design and engineering services for bridge 05655. Value $192,000 CTDOT. Total project value $240,000.
Mill Street Bridge - Design and engineering services for bridge 05314. Value $192,000 CTDOT. Total project value $240,000.
West Main Street and Sidewalks on Green - Reconstruct West side of Main street and sidewalks on the Green. Value $251,234 Total project value $363,734. OPM-STEAP grant monies.
Grove Street - [Anderson Avenue to Frank's Lane] 7900' - Resurfacing and safety improvements to roadway. Value $540,000. CTDOT
Boardman Road - Resurfacing and safety improvements to approximately 1000' of roadway. Value $90,000. CTDOT
Richmond Center Re-Pointing - Repointing a portion of the exterior brick surface. Value $76,000. DECD Program Income Reuse. Total Project value $100,000.
East Street Sidewalks 4-2010 - notice to bidders
Plans for East Street-not a complete set are below: They will take time to load.
Middle Section
Southerly Section
General Details
Project Notes
Proposed Middle Section
Proposed Southerly Section
East Street Title
Traffic Control Plan
|